NAMES
|
Job
Description
|
| Cam
Component Alloy Mfg Sdn Bhd, Alor Gajah,
Melaka |
September
1999- Design, Engineering, Procurement,
Fabrication, Installation, Testing and
Commissioning of Internal Piping System |
| W.R.
Grace Specialty Chemical (M) Sdn Bhd, Gebeng,
Kuantan |
September
1999 - Design, Engineering, Procurement,
Fabrication, Installation, Testing and
Commissioning of Internal Piping System |
| Tractors
(M) Sdn Bhd |
October
1999 - Fabrication & Assembly of Natural
Gas Station (District Station - 4 units) |
| Tractors
(M) Sdn Bhd |
December
1999 - Fabrication & Assembly of Natural
Gas Station (TG & Flexitech) |
| Alwich
Enviro-Management Sdn Bhd, Kemaman, Trengganu |
March
2000 - Design, Engineering, Procurement,
Fabrication, Installation, Testing and
Commissioning of Internal Piping and LPG
Manifold System |
| Tractors
(M) Sdn Bhd |
April
2000 - Fabrication & Assembly of Natural
Gas Station (D500 & D100 - 25 units) |
| Petronas
NGV Station, Putrajaya |
May
2000 - Fabrication , Assembly &
Installation of NGV Refueling Station |
| Wisma
Putrajaya |
May
2000 - Design, Engineering, Procurement,
Fabrication, Installation, Testing and
Commissioning of Installation of Underground
Diesel Tank and related piping system |
| BP
Malaysia Sdn Bhd |
May
2000 - Installation of 2x2.5KL LPG Tank and
related piping system (Shimano Components (M)
Sdn Bhd, Pontian, Johor) |
| Petronas
NGV Station, Tampin, Senawang |
May
2000 - Fabrication , Assembly &
Installation of NGV Refueling Station |
| BP
Malaysia Sdn Bhd |
May
2000 - Installation of 4x20kg LPG pig tank and
related piping system (Kejuruteraan Letrik
S/B, Shah Alam |
| BP
Malaysia Sdn Bhd |
May
2000 - Installation of Manifold System and
related piping system (GB Industries Sdn Bhd,
Petaling Jaya, Selangor |
| BP
Malaysia Sdn Bhd |
June
2000 - Installation of 2x2.5KL LPG Tank and
related piping system (Power Season Metal (M)
Sdn Bhd, Muar, Johor |
| BP
Malaysia Sdn Bhd |
June
2000 - Installation of 2x2.5KL LPG Tank and
related piping system (Fiber Plus Sdn Bhd,
Muar, Johor) |
| BP
Malaysia Sdn Bhd |
July
2000 -Installation of 1x2.5KL LPG Tank and
related piping system (Ayer Keroh Resort,
Melaka) |
| Yi-Lai
Berhad, Kulai, Johor |
August
2000 - Design, Engineering, Procurement,
Fabrication, Installation, Testing and
Commissioning of Internal Piping System |
| Raza
Manufacturing Bhd, Bangi |
August
2000 - Installation of one unit Kawasaki
Absorption Chiller |
| Petronas
NGV Station, Puchong, Selangor |
August
2000 - Fabrication, Assembly &
Installation NGV Refueling Station |
| Tractors
(M) Sdn Bhd |
September
2000 - Fabrication & Assembly of Natural
Gas Station (D500 & D100 & Regulation
Station & District Station - 21 units) |
| BP
Malaysia Sdn Bhd |
September
2000 - Installation of 2x2.5KL LPG Tank and
related piping system (Concorde Hotel Shah